Linking tasks can help you save time as you manage your project. After you define your project's tasks and estimate how long they will take, you are ready to link them.
Linking tasks creates a plan based on sequence and dependencies, regardless of specific dates. A plan like this can easily adjust to schedule changes
while preserving the relationships between tasks. If the start date, duration, or finish date of one task changes, Project automatically reschedules all related tasks. Linking makes your plan more flexible and more reliable.