Plan projects and analyze dependencies with a Visio PERT chart

Applies to:

Applies to
Microsoft Office Visio® 2003
Microsoft Visio 2002

You can organize tasks, establish timeframes, and illustrate dependencies at the start of a project with Visio Program Evaluation and Review Technique (PERT) charts.

Or, you can illustrate the steps to a specific goal. For example, a PERT chart could outline the steps required for your department to meet its two-year revenue objectives.

This article describes how to:


PERT chart example

In a PERT chart, each rectangular shape, or node, represents a task. The connections between tasks indicate dependencies.

Create a PERT chart structure

Each project task or step is represented by a node. Nodes are divided into sections where you can record task data.

First, you'll drag a node for each task onto the drawing page. Then, you'll connect the nodes to indicate the order in which the tasks must be completed and the dependencies between them.

To create a PERT chart structure

  1. In Visio, on the File menu, point to New, point to Project Schedule, and then click PERT Chart.
  2. From the PERT Chart Shapes stencil, drag a PERT 1 or PERT 2 shape onto the drawing page to create the first node.
  3. Drag a second PERT 1 or PERT 2 shape onto the drawing page to create the second node.
  4. Drag a Dynamic connector shape onto the drawing page.
  5. Click away from the connector to see which end has an arrowhead. Then select the connector and drag the end without the arrowhead to the middle of the first node until a red box appears around the entire shape.
    PERT chart connector
  6. Connect the other end of the connector to the second node the same way.

The shapes stay connected at the closest available points when you move them.

  1. Continue dragging and connecting node shapes until each of your project tasks or steps is represented by a node.

Add information to a PERT chart

You can add task information to the nodes and to the connectors between the nodes.

To add task information to a node

  1. Click a node to select it.
  2. Type the name of a task to replace the node's default text.
  3. Click one of the node's subdivisions to select it, and then type the text you want to replace the default text.

 Note    Use the default text in a node subdivision only as a guideline for the type of information you might add. For example, in the subdivision of the PERT 2 shape named Scheduled Finish, you can type the task's duration, or any other text pertinent to the task.

  1. Repeat step 3 until you have replaced all the default text in each node.

 Tip    To delete the default text and leave a node's subdivisions empty, select a subdivision, and then press the SPACEBAR.

To add text to a connector

  1. Click a connector to select it.
  2. On the connector, type the text you want to see.

Refine a PERT chart

Goal Take this action
Change the task name in a node
  • Click the node with the task name you want to change, and then type a new task name.
Revise text in a node subdivision
  • Click the node that contains the subdivision, click the subdivision, and then type new text.
Revise text on a connector
  • Click the connector to select it, and then type new text.
Move a node
  • Click the node to select it, and then drag it to a new location.

 Note    If you don't like the path the connector takes after you move a node, place the pointer over one of the connector's end points, and then drag it to a new connection point (blue x) on the node. Make sure that you see a red square around the new connection point.

Delete a node
  • Click the node to select it, and then press the DELETE key.

 Note    If you're not replacing the node with a new one, click the connector that pointed to the node, and then press DELETE again.

Create a hierarchical summary of a project

You may want to brainstorm about the project's tasks and create a picture of how the tasks relate to one another before you start scheduling. You can use a specially designed shape on the PERT chart stencil to quickly create a hierarchical task summary.


Hierarchical summary of project tasks

You can map out the relationships between the tasks in a project using the Summarization structure shape from the PERT Chart Shapes stencil.

To create a hierarchical task summary

  1. In Visio, on the File menu, point to New, point to Project Schedule, and then click PERT Chart.
  2. Drag a Summarization structure shape from the PERT Chart Shapes stencil onto the drawing page.
  3. Drag a second Summarization structure shape onto the drawing page and place it beneath the first shape.
  4. Drag the control handle from the second shape, and glue it to a connection point on the bottom of the first shape.
  5. Continue dragging Summarization structure shapes and gluing their control handles to shapes higher in the hierarchy until you've documented all the tasks in your project.

More information

For instructions about adding annotations to a PERT chart and improving the way a chart looks, see Prepare Visio 2003 schedule drawings for presentation.

 
 