After you install Project Server 2003, a single Enterprise
Calendar is available for use. This is the Standard Enterprise
Calendar. Characteristics of the Standard Enterprise Calendar
include:
- It cannot be deleted All custom Enterprise Calendars are copies based on the Standard Enterprise Calendar.
- It is locale-dependent The Standard Enterprise Calendar
in the United States is a 40-hour week calendar with Monday through
Friday specified as working days, and 8:00 A.M. to 5:00 P.M.
specified as the working times with an hour break.
- It describes the basic working week You can use
Project Server 2003 immediately upon installation without the
need to create custom Enterprise Calendars.
- It can be edited The Standard Enterprise Calendar can
be edited either in the Enterprise Global Template, or within a
local project (if local edits of Enterprise Calendars are allowed
in your organization).