Quiz: Linking tasks in Project 2003
Office quiz logo
Save time as you manage your project by linking tasks. Then your plan easily adjusts to schedule changes while preserving the relationship between tasks.

Content in this quiz was excerpted from Training on Office Online.

Download a free trial of Office 2007—and get access to training courses
Office Online Training logo
See all Office quizzesE-mail this quiz
1. If you're not certain how the work of Task 1 relates to the work of Task 2, which dependency type should you create?
 
a.
b.
c.
d.
 
2. It will take a writer 12 days to write a manual and an editor 6 days to edit it. Which type of dependency will get the work completed in the shortest possible time?
 
a.
b.
c.
 
3. The Predecessors column for Task 10 contains this text: 7FF,5,6SS. Which explanation correctly describes Task 10's dependencies?
 
a.
b.
c.
 
4. The task "Select Pictures" must be completed at least one week before the task "Presentation" finishes. Which dependency type and lag time or lead time will get all the work done in the shortest possible time?
 
a.
b.
c.
 
5. The task "Write Manual" will take 15 days, and the task "Edit Manual" will take 12 days. Which dependency type and lag time or lead time will get all of the the work done in 18 days?
 
a.
b.
c.
 