If you know the amount of work (work: For tasks, the total labor required to complete a task. For assignments, the amount of work to which a resource is assigned. For resources, the total amount of work to which a resource is assigned for all tasks. Work is different from task duration.) that has been performed on a task (task: An activity that has a beginning and an end. Project plans are made up of tasks.), you can enter the actual work (actual work: The amount of work that has been performed on a task or assignment. When you enter actual work on a task, the remaining work is calculated using this formula: Remaining Work = Work - Actual Work. Actual work is often referred to as "actuals.") for the task.
- On the View menu, click More Views.
- In the Views list, click Task Sheet, and then click Apply.
- On the View menu, point to Table, and then click Work.
- In the Actual
field (field: A location in a sheet, form, or chart that contains a specific kind of information about a task, resource, or assignment. For example, in a sheet, each column is a field. In a form, a field is a named box or a place in a column.) of the tasks you want to update, enter the actual work values.
The recalculated values for percentage of work complete and remaining work appear in the % W. Comp. (Percent Work Complete) and Remaining (Remaining Work) fields, respectively. Press TAB to move to the field if it's not visible.
Note When you specify the actual work for a task, Microsoft Office Project 2003 calculates the percentage of work complete (percent work complete: A percentage value that indicates the current status of a task, resource, or assignment, expressed as the percentage of work that has been completed.) and remaining work (remaining work: The amount of work, in terms of a time unit such as hours or days, that is left to be completed on a task. This is calculated as follows: Remaining Work = Work - Actual Work.) according to the formulas Percent Work Complete = Actual Work / Work and Remaining Work = Work - Actual Work.