 |
Record progress At this point in the schedule, you need to enter progress or some other change in task status in the project plan and communicate that change to team members.
Note If you assign resources to tasks, you can track task durations, start and finish dates, costs, and work at both the task and assignment levels. If you don't assign resources to tasks, you cannot track work at the assignment level and you must record progress manually.
-
Record progress if resources are not assigned to tasks
Click all of the following that apply:
- Update work on a project to update actual (actual: Information that shows what has actually occurred. For example, the actual start date for a task is the day that the task actually started.) start (start date: The date when a task is scheduled to begin. This date is based on the duration, calendars, and constraints of predecessor and successor tasks. A task's start date is also based on its own calendars and constraints.) and finish dates (finish date: The date that a task is scheduled to be completed. This date is based on the task's start date, duration, calendars, predecessor dates, task dependencies, and constraints.), actual work (actual work: The amount of work that has been performed on a task or assignment. When you enter actual work on a task, the remaining work is calculated using this formula: Remaining Work = Work - Actual Work. Actual work is often referred to as "actuals."), actual duration (actual duration: The amount of time a task has been in progress. When you enter the actual duration of a task, Project uses this value to calculate the remaining duration according to the formula Remaining Duration = Duration - Actual Duration.), remaining duration (remaining duration: The amount of time left to work on a task before the task is completed. This is calculated as follows: Remaining Duration = Duration - Actual Duration.), percent complete (percent complete: A field that you use to enter or display how much of a task has been completed. This value is expressed as the percentage of the task duration that has been completed.), or percent work complete (percent work complete: A percentage value that indicates the current status of a task, resource, or assignment, expressed as the percentage of work that has been completed.). Be aware, however, that percent complete, actual duration, and remaining duration are interlocking quantities; updating one of them might cause the values of the others to change.
- Update completed tasks quickly to show that a task is 100% complete.
- Update costs to track the real costs of tasks or resource assignments (assignment: A specific resource that is assigned to a particular task.).
-
Record progress if resources are assigned to tasks
Click all of the following that apply:
- Publish the latest plan and team assignments if you are using Microsoft Office Project Professional 2007
and want to inform team members of schedule changes that might affect them, such as a new task start date or an increase in the amount of time they're assigned to a task.
- Update work on a project to update actual
start and finish dates, actual work, actual duration, remaining duration, percent complete, or percent work complete. Be aware, however, that percent complete, actual duration, and remaining duration are interlocking quantities; updating one of them might cause the values of the others to change.
- Update completed tasks quickly to show that a task is 100% complete.
- Update costs to track the real costs of tasks or resource assignments.
Respond to incomplete, new, or changed work You need to make sure that your team completes all planned work and that you can flexibly respond to any unplanned changes.
Click all of the following that apply:
Update original estimates If you find that actual project progress is so different from the baseline estimates as to make comparison between the two meaningless, you need to update the original estimates.
Click all of the following that apply:
|