Identify overallocated or underallocated resources Review the resource workload for the project plan that you just built. Although some overallocation or underallocation might be normal in certain circumstances, this review can help you to see whether your resources are acceptably allocated or whether you need to make further adjustments to the resource workload.
Account for overallocations by adding overtime
You can add overtime to tasks that are assigned to overallocated resources. Although overtime (overtime: The amount of work on an assignment that is scheduled beyond the regular working hours of an assigned resource and charged at the overtime rate. Overtime work indicates the amount of the assignment's work that is specified as overtime work.) doesn't resolve overallocations, it ensures that resources have a way to work the time represented by the overallocation. This is often the best strategy when faced with overallocations, although it will be costly.
Resolve resource overallocations
The Leveling (leveling: Resolving resource conflicts or overallocations by delaying or splitting certain tasks. When Project levels a resource, its selected assignments are distributed and rescheduled.)
feature in Project can even out the resource workload for you. Or,
you can manually adjust resource availability (availability: Indicates when and how much of a resource's time can be scheduled for assigned work. Availability is determined by project and resource calendars, resource start and finish dates, or the level at which the resource is available for work.), assignment details, and task details to relieve overallocations and balance the workload.
Click all of the following that apply:
Resolve resource underallocations
You can adjust resource availability, assignment details, and task details to balance the workload and maximize underallocated project resources. Note that underallocations are often valid and temporary, based on resource availability and skill set, task constraints (constraint: A restriction set on the start or finish date of a task. You can specify that a task must start on or finish no later than a particular date. Constraints can be flexible [not tied to a specific date] or inflexible [tied to a specific date].), and the many other factors that go into scheduling a project.
Click all of the following that apply:
Enter a note about resource, assignment, and task changes Log information about changes you made to optimize the resource workload. Such notes can be helpful when you're tracking actual progress, closing the project, or collecting data for the next project.
Evaluate the results of resource optimization
Check to ensure that you did indeed resolve resource allocation problems and that the finish date, planned costs, and other projects were not adversely affected by these changes.
Click all of the following that apply:
Communicate assignment changes If you assigned new tasks to resources or changed or removed existing assignments as a result of optimizing the resource workload, notify the affected resources, either electronically or by printing assignment reports.
|