 |
Specify
and review project dates
Reviewing project dates can help you to see whether you
are meeting the targeted finish date and whether you need to make any further adjustments to meet that date.
Click all of the following that apply:
Identify the critical path If you
are not meeting your targeted finish date, seeing the critical path (critical path: The series of tasks that must be completed on schedule for a project to finish on schedule. Each task on the critical path is a critical task.) can help you to focus on adjusting calendars (calendar: The scheduling mechanism that determines working time for resources and tasks. Project uses four types of calendars: the base calendar, project calendar, resource calendar, and task calendar.), scope (scope: The combination of all project goals and tasks, and the work required to accomplish them.), tasks (task: An activity that has a beginning and an end. Project plans are made up of tasks.), and assignments (assignment: A specific resource that is assigned to a particular task.) to make changes to the critical path tasks and therefore the finish date.
Estimate durations by using PERT analysis The duration (duration: The total span of active working time that is required to complete a task. This is generally the amount of working time from the start to finish of a task, as defined by the project and resource calendar.) estimation tools in Project can help you to develop realistic durations for the tasks in your project plan.
Adjust the plan to meet the finish date
You can use a variety of strategies,
including adjusting calendars, scope, tasks, and assignments, to meet the targeted finish date.
Click all of the following that apply:
Adjust the plan to take advantage of additional time
More . . .
After you build your plan and Project calculates the schedule (schedule: The timing and sequence of tasks within a project. A schedule consists mainly of tasks, task dependencies, durations, constraints, and time-oriented project information.) and cost (cost: The total scheduled cost for a task, resource, or assignment, or for an entire project. This is sometimes referred to as the current cost. In Project, baseline costs are usually referred to as "budget.") for the project, you might have more time or an increased budget (budget: The estimated cost of a project that you establish in Project with your baseline plan.). You can choose to end the project ahead of schedule or under budget. Or, you can increase the scope (scope: The combination of all project goals and tasks, and the work required to accomplish them.) and add quality (quality: The degree of excellence, or the desired standards, in a product, process, or project.) to the project deliverables.
-
Check with the customers If appropriate, check with the customers or stakeholders (stakeholders: Individuals and organizations that are actively involved in the project or whose interests may be affected by the project.) to see how they prefer to use the time or budget. They might prefer to leave the plan as is and have the project come in ahead of schedule or under budget.
-
Check your contract See if there are contractual incentives (or in some cases, even penalties) for coming in ahead of schedule or under budget. The type of contract you have (fixed price, cost reimbursable, or unit price) can help you determine how you can take advantage of available time or budget.
-
Add scope If you have extra time or budget available, you can add tasks (task: An activity that has a beginning and an end. Project plans are made up of tasks.) or phases (phase: A group of related tasks that completes a major step in a project.)
that you wanted to implement but thought you wouldn't have enough time or money for. You can increase duration (duration: The total span of active working time that is required to complete a task. This is generally the amount of working time from the start to finish of a task, as defined by the project and resource calendar.) on existing tasks so that resources (resources: The people, equipment, and material that are used to complete tasks in a project.) have more time to complete them. Be aware that adding scope is likely to add both time and cost to your plan. Changing the scope and deliverables (deliverable: A tangible and measurable result, outcome, or item that must be produced to complete a project or part of a project. Typically, the project team and project stakeholders agree on project deliverables before the project begins.) may have contractual implications, so be sure to check the contract and obtain client approval when necessary.
-
Raise the standard of quality You can use surplus time or budget to add tasks or phases that add or check for quality. You can increase duration on existing tasks, so that resources have more time to do higher quality work. Another way to raise quality is to add more highly skilled staff, more efficient equipment, or higher grade materials. These types of resources can be more expensive, but they can also be a good use of surplus budget.
Enter a note about schedule changes
Log information about changes you made to meet the finish date. Such notes can be helpful when you
are tracking actual progress, closing the project, or collecting data for the next project.
Evaluate the results of schedule optimization
This evaluation
ensures that you did indeed meet the finish date and that costs, workload, and other projects were not adversely affected by these changes.
Click all of the following that apply:
Communicate assignment changes to resources If you assigned new tasks to resources (resources: The people, equipment, and material that are used to complete tasks in a project.) or changed or removed existing assignments as a result of meeting the finish date, you can communicate these changes to the affected resources, either online or by printing assignment reports (report: A format in which you can print schedule information that is appropriate for the intended recipients. You can use the predefined reports provided by Project or create custom reports.).
|