Change the resource details

Sometimes, when resources are imported into Microsoft Office Project Server, the information about them needs to change because of changes in the organization or in the status of the resources. You can change information about resources, such their as e-mail address, active status, booking type, availability, and cost center.

 Note   Some information about resources, such as their work schedule, can be changed only by using Microsoft Office Project Professional. To change this information, select the resource, and then click Open. Project Professional opens with the Resource Sheet displayed. Within Project, make the changes for the resource, and then click Save on the File menu.

  1. On the Quick Launch, click Resources.
  2. To display a list of resources in the View box, select one of the following resource types:
    • All Resources    If you want to view all the enterprise resources in the organization, select this option.
    • Cost Resources    If you want to view resources that don't depend on the amount of work on a task or the duration of a task, such as airfare or lodging, select this option.
    • Material Resources    If you want to view consumable materials or supplies, such as concrete, wood, or nails, select this option.
    • Work Resources    If you want to view the people and equipment that perform work to accomplish a task, select this option.
  3. In the table, select the resource whose information you want to change, and then click Edit Details.

 Tip   To select adjacent resources, hold down SHIFT, and then click the first resource and last resource. To select nonadjacent resources, hold down CTRL, and then click the resources that you want. You can change the information for each resource in turn.

You can change the following items:

To allow the resource to be assigned to tasks, select the Can be assigned as a project resource check box.

You can choose whether the resource is committed (committed resource: A resource that is formally allocated to any task assignments they have within a project. This is the default booking type.) or proposed (proposed resource: A resource with a pending resource allocation to a task assignment that has not yet been authorized. This resource assignment does not detract from the availability of the resource to work on other projects.) to work on a project by choosing the Default Booking Type box.

To specify the assignment owner, in the Default Assignment Owner box, type or search for the assignment owner's name. Typically, the assignment owner is the work resource who was initially assigned to the task.

  1. Your organization may require additional information about your resources. Under Resource Custom Fields, enter the information that your organization requires for each resource.
  2. Click Save. If you selected multiple resources, click Save/Next to change the information for the next resource.

 Note   You can also change the same information for multiple resources at one time by selecting the resources and then clicking Bulk Edit on the Actions menu. You cannot bulk edit information that is specific to individual resources.

ShowWhy can't I perform some actions in Microsoft Office Project Web Access?

Depending on the permissions settings you used to log on to Project Web Access, you may not be able to see or use certain features. Also, what you see on some pages may differ from what is documented if your server administrator customized Project Web Access and did not customize the Help to match.

Top of Page Top of Page

 
 