Applies to: Microsoft Office Project 2007
You can set a baseline (baseline plan: The original project plans [up to 11 per project] used to track progress on a project. The baseline plan is a snapshot of your schedule at the time that you save the baseline and includes information about tasks, resources, and assignments.) for your project, enabling you to compare your progress with the original plan and any additional baselines you set at milestones throughout your project.
In this demo, I set a baseline for specific tasks within my project.