Troubleshoot working with costs

ShowMy cost totals are incorrect.

If the expected amount of a task's total cost (total cost: The calculated cost of a project, task, resource, or assignment over the life of the project.) differs from the calculated sum of its various rate-based (rate-based cost: Costs that are based on a rate that you enter in the Costs tab of the Resource Information dialog box.), per-use (per-use cost: A set fee for the use of a resource that can be in place of, or in addition to, a variable. For work resources, a per-use cost accrues each time that the resource is used. For material resources, a per-use cost is accrued only once.), and fixed costs (fixed cost: A set cost for a task that remains constant regardless of the task duration or the work performed by a resource.), do the following:

A different cost rate table (cost rate table: A collection of information about a resource's rates, including the standard rate, overtime rate, any per-use cost, and the date when the pay rate takes effect. You can establish up to five different cost rate tables for each resource.) may be applied. Correct this problem by changing the cost rate tables on a resource assignment.

A rate change you specified in the cost rate table may have gone into effect.

  • Check task cost totals. Tasks may have a fixed cost you forgot about.

ShowMy cost totals changed unexpectedly.

If task cost totals (total cost: The calculated cost of a project, task, resource, or assignment over the life of the project.) have changed even though you haven't entered new costs or updated them, do the following:

  • Check the new date range of a task you moved. If you moved a task into a different time frame, a different rate you set for that time frame may have been applied.

ShowMy resource assignment cost shows a zero value.

ShowMy costs don't accrue as set by default.

When you import files in MPX format (MPX file format: The Microsoft Project Exchange [MPX] file format is a record-based ASCII text format that is used to import data into Project.) from an earlier version of Microsoft Office Project 2003, the accrual method (accrual method: Determines when the cost for a resource is incurred and when actual costs are charged to a project. You can incur costs at the start [Start] or finish [End] of a task or prorate them [Prorated] during the task.) of the earlier version may overwrite the current version's prorated default method if the older version has a different default accrual method. You may want to manually adjust accrual methods.

ShowThe overtime rates are not incorporated in cost totals.

ShowI can't enter actual costs into my project.

By default, Microsoft Office Project 2003 automatically calculates actual costs (actual cost: The cost that has actually been incurred to date for a task, resource, or assignment. For example, if the only resource assigned to a task gets paid $20 per hour and has worked for two hours, the actual cost to date for the task is $40.). If you want to edit actual cost information, you need to turn off the automatic calculation of actual costs.

  1. On the Tools menu, click Options, and then click the Calculation tab.
  2. Clear the Actual costs are always calculated by Microsoft Office Project check box.
 
 
Applies to:
Project 2003