Set lead or lag time between tasks

You can set lead time (lead time: An overlap between tasks that have a dependency. For example, if a task can start when its predecessor is half-finished, you can specify a finish-to-start dependency with a lead time of 50 percent for its successor [has a negative lag value].) or lag time (lag time: A delay between tasks that have a dependency. For example, if you need a two-day delay between the finish of one task and the start of another, you can establish a finish-to-start dependency and specify a two-day lag time [has a positive value].) between tasks only after creating task dependencies (task dependencies: A relationship between two linked tasks; linked by a dependency between their finish and start dates. There are four kinds of task dependencies: Finish-to-start [FS], Start-to-start [SS], Finish-to-finish [FF], and Start-to-finish [SF].).

  1. On the View menu, click Gantt Chart.
  2. In the Task Name field, select the task you want to set lead or lag time for, and then click Task Information Button image.
  3. Click the Predecessors tab.
  4. In the Lag field, type the lead time or lag time you want as a duration (duration: The total span of active working time that is required to complete a task. This is generally the amount of working time from the start to finish of a task, as defined by the project and resource calendar.) or as a percentage of the predecessor (predecessor: A task that must start or finish before another task can start or finish.) task duration.
    • To enter lead time, type a negative number or negative percentage, such as -2d for two days of lead time.
    • To enter lag time, type a positive number or percentage, such as 50% for half the predecessor task's duration in lag time.

 Note   You can quickly add lead or lag time to a successor (successor: A task that cannot start or finish until another task starts or finishes.) task by double-clicking the link line on the Gantt Chart, and then typing the amount of lead or lag time in the Lag box.

 
 
Applies to:
Project 2003