Linking Project tasks

Dependency type definitions

These four dependency types can help you schedule your real-world situation.

A predecessor is a task whose start or finish date determines the start or finish date of its successor task.

A successor is a task whose start or finish date is driven by its predecessor task.

The nature of the relationship between a predecessor task and a successor task determines the type of task dependency to use.