Page 10 of 20PREVNEXT

Linking Project tasks

Use the Link Tasks button

When you link two tasks, Project creates a Finish-to-Start dependency by default.

Feeling creative? It's time you learned how and when to create links between tasks in Project. Whether you prefer to type or point and click, there's a method to suit you.

Once you know how to link tasks, think about when to link them. If you move a task or insert a new task, Project automatically links it in the same way as the tasks around it. By getting all of your tasks in order first, you make sure that the link you like stays just the way you want it.