|
Resolve resource overallocations When a resource is assigned too much work in a given period, the most effective way to reallocate or reschedule the work is to look at all pertinent details and decide yourself which tradeoff to make.
Click all of the following that apply:
Click all of the following that apply:
Resolve resource overallocations by leveling Project can automatically level an overallocated resource's workload by delaying (delay: The amount of time between the scheduled start of a task and the time when work should actually begin on the task; it is often used to resolve resource overallocations. There are two types of delay: assignment delay and leveling delay.) or splitting tasks until the resource is no longer overallocated.
Resolve resource underallocations To maintain progress on tasks, you need to make sure that resources are assigned to work consistently throughout the project and are not underutilized when work is needed.
Click all of the following that apply:
Click all of the following that apply:
Add a note about resource changes You may want to record changes that were made to resource assignments and the reasons for those changes so that you can remember details if you work on a similar project in the future or conduct a lessons-learned (lessons learned: A review of best practices, project insights, and client information. As the project team disbands and new projects begin, reviewing the lessons learned lets you record information gathered and generated through the project.) exercise at the end of the project.
Evaluate the results of resource adjustments After you level (leveling: Resolving resource conflicts or overallocations by delaying or splitting certain tasks. When Project levels a resource, its selected assignments are distributed and rescheduled.) the schedule (schedule: The timing and sequence of tasks within a project. A schedule consists mainly of tasks, task dependencies, durations, constraints, and time-oriented project information.) and correct any overallocations or underallocations, you should review the schedule to ensure that you will still meet the budget (budget: The estimated cost of a project that you establish in Project with your baseline plan.) and planned finish date for the project and any related projects.
Click all of the following that apply:
Compare two versions of a project and report differences If you have saved a backup copy of the plan, you can compare specific fields (field: A location in a sheet, form, or chart that contains a specific kind of information about a task, resource, or assignment. For example, in a sheet, each column is a field. In a form, a field is a named box or a place in a column.) to ensure that the changes you made are what you intended.
|