Finish (resource field)

Data Type    Date (date field: A type of field whose content is a date. Examples include the Baseline Start and Early Finish fields.)

Entry Type    Calculated (calculated field: A field in which the value is determined by Project based on information in other fields. Project may recalculate the value automatically or when you specify, depending on your choice of calculation settings.)

Description    The Finish field shows the date when a resource is scheduled to complete work on all assigned tasks.

How Calculated    Microsoft Office Project calculates the resource finish date as the latest finish date of all assignments for the resource.

Best Uses    Add the Finish field to a resource view to see or filter for latest finish dates for resources.

Example    You need to see when Jamie is scheduled to finish the last of 10 assigned tasks. In the Resource Sheet view, you add the Finish field. You see the latest scheduled finish date of all of Jamie's assignments.

 
 
Applies to:
Project Professional 2013, Project Standard 2013, Project 2010, Project 2007, Project 2003