Create task dependencies (links) across projects

After tasks (task: An activity that has a beginning and an end. Project plans are made up of tasks.) are created in a project, they need to be linked (linking: In a project, establishing a dependency between tasks. Linking tasks defines a dependency between their start and finish dates. In OLE, establishing a connection between programs so that data in one document is updated when it changes in another.) to show relationships between them. You can link the tasks within a project or across projects. Linking tasks creates task dependencies (task dependencies: A relationship between two linked tasks; linked by a dependency between their finish and start dates. There are four kinds of task dependencies: Finish-to-start [FS], Start-to-start [SS], Finish-to-finish [FF], and Start-to-finish [SF].).

 Tip   You can also show relationships between multiple projects by using inter-project dependencies.

ShowWhen should I use cross-project links, instead of inter-project dependencies?    

If your project has a specific task that depends on a specific task in another project, use cross-project links to tie the task dates to one another. This way, if the task that you are dependent upon slips, the new dates are reflected in your own task. If your project is dependent on some aspect of another project, and the dependency is not necessarily tied to a specific task, use inter-project dependencies to identify exactly what each project brings to the relationship.

  1. Open both projects: the project that contains the task that you want to link to and the project that contains the task that you want to link from.

On the Window menu of one of the projects, click Arrange All.

  1. Click the task for which you want to create a dependency to an external predecessor.
  2. Click Task Information Button image, and then click the Predecessors tab.
  3. In the ID column, type the project name and task ID number of the external predecessor, separated by a backslash. For example, type Project1\1 for task ID 1 in a file named Project1.

By default, you are notified if the data in an externally linked project has changed. The external predecessors and successors and the impacts to your schedule are displayed when you open a project with external links, and you can choose to accept any or all changes.

 Notes 

  • Both projects must be saved before you can link to an external task.
  • When you link tasks in different projects that are stored in Microsoft Office Project Server, the predecessor's task ID must be formatted correctly. In the Task Information dialog box, on the Predecessors tab, in the ID column, the task ID must be formatted as shown in the following example: <>\project1\42. In this example, project1 is the name of the project that contains the predecessor, and 42 is the task ID of the predecessor task.
  • Externally linked tasks appear dimmed in the task list. Double-clicking a task with an external successor or an external predecessor opens the project that contains the external task, if the project is available.

ShowI linked tasks between projects, but the data doesn't match.

When you use the Paste Link option in the Paste Special dialog box (Edit menu) to connect tasks, Project uses Object Linking and Embedding (OLE) to make the connection. Only the fields that you have selected are linked. However, a task may have many more fields of information associated with it that affect how the task is scheduled, and these fields may be hidden if you have a split-screen view.

If you need to create a dependency between tasks in different projects, create external dependencies (instead of pasting a link) to maintain an accurate schedule.

When you use the Paste Link option, select individual fields instead of entire rows, and link only as much information as is needed to avoid conflicting schedule information.

Top of Page Top of Page

 
 
Applies to:
Project 2007