Assignment Owner (assignment field)

Data Type    Enumerated (enumerated field: A type of field whose content is selected from a list of predefined choices. For example, in the Accrue At field you can select the way resource costs are accrued from a list that includes Start, Prorated, and End.)

Entry Type    Calculated or entered (calculated or entered field: A field in which the value is determined by Project based on information in other fields. Information that you enter in the field yourself overrides calculated values.)

Description    The Assignment Owner field contains the name of the user who is responsible for entering status in Project Web App for the current assignment (assignment: A specific resource that is assigned to a particular task.).

How Calculated    Work resources (work resource: People and equipment resources that perform work to accomplish a task. Work resources consume time [hours or days] to accomplish tasks.) own their own assignments by default. Assignments with material resources (material resource: The supplies or other consumable items that are used to complete tasks in a project.) and generic resources (generic resources: Placeholder resources that are used to specify the skills required for a specific task.) are owned by the default assignment owner (assignment owner: An enterprise resource who is responsible for entering progress information in Project Web Access. This person can be different than the person initially assigned to the task.), if one is identified. If there is no default assignment owner, the Assignment Owner field contains the name of the person who created the project plan. This field can be changed to any work resource who is a part of the project team. Cost resources (cost resources: Resources that don't depend on the amount of work on a task or the duration of a task, such as airfare or lodging.) do not have assignment owners.

Best Uses    Add the Assignment Owner field to the Task Usage or Resource Usage view when you need to review or update the name of the individuals who are to enter status for the assignments. Update this field if a team member other than the assigned work resource will be entering status for the assignment, or if there are multiple assigned resources, and one of them is to be responsible for reporting status in Project Web App. Specify an assignment owner if the resource does not have a default assignment owner or if you want to change it.

Example    Wilson is assigned to a number of tasks in the project. For five of these tasks during the month of July, he will be working away from the office and unable to access a computer to report on his assignment status. His manager, Pilar, is available during that time period, so she has set herself to be the assignment owner for those five assignments. Pilar will then be able to enter status information for Wilson on those assignments.

In your construction project, you have two resources assigned to all tasks having to do with laying brick: the work resource Keith, the bricklayer, and the material resource "Bricks." In addition to being the assignment owner for his work assignments, Keith has also been designated the assignment owner for the "Bricks" assignments. When reporting assignment status, Keith enters the number of hours he has worked on his assignments. He also enters the number of bricks he has used in the fulfillment of these assignments.

Remarks    Team members who are identified as assignment owners can see the assignment in Project Web App.

You can set the assignment owner for an individual assignment using the Assignment Information dialog box.

You can set the assignment owners for all resources assigned to a single task through the Task Information dialog box.

The Assignment Owner field is not available for local (non-enterprise) resources.

 
 