Before your project gets rolling, you will probably want to mark its major goals with milestones (milestone: A reference point marking a major event in a project and used to monitor the project's progress. Any task with zero duration is automatically displayed as a milestone; you can also mark any other task of any duration as a milestone.). The quickest way to create a milestone is to add a task (task: An activity that has a beginning and an end. Project plans are made up of tasks.) with no duration to your project plan.
- Click View, and then in the Task Views group, click Gantt Chart.
- Type the milestone name in the first empty row or pick a task you want to turn into a milestone.
- Type 0 in the Duration field, and then press Enter.
The milestone symbol is now part of your Gantt Chart.
Also in this article
Add a milestone with a duration
Sometimes a milestone takes time. For example, the approval process at the end of a phase might take a week, so that milestone would need to take place over time like a normal task.
- Click View, and then in the Task Views group, click Gantt Chart.
- Type the milestone name in the first empty row or pick a task you want to turn into a milestone.
- Select the milestone, and then click Task. In the Properties group, click Task Information.
- Click the Advanced tab, and then type the milestone duration in the Duration box.
- Check Mark task as milestone, and then click OK.
On the Gantt Chart, the milestone symbol appears on the last day of the task. It doesn’t appear as a bar, even though it has duration.
Top of Page
Add an external milestone
Sometimes you might need a milestone to track a task that’s outside the scope of your project.
- If the milestone depends on a project that is beyond your control, such as software that is being developed by another company, create a milestone using the steps in the previous section. You’ll have to keep an eye on the external task and update it manually.
- If the milestone is part of a project in your organization, you can track it with a cross-project link.
Top of Page