- On the View menu, click Gantt Chart.
- In the Task Name field, select the tasks you want to unlink.
- Click Unlink Tasks
.
The tasks are rescheduled based on any links to other tasks or constraints (constraint: A restriction set on the start or finish date of a task. You can specify that a task must start on or finish no later than a particular date. Constraints can be flexible [not tied to a specific date] or inflexible [tied to a specific date].).
Note Removing a task link removes the dependency between two tasks, as indicated by the link lines between the tasks. If you want to change the hierarchical structure of a task or subtask as part of an outline structure for your project, then you need to outdent the task rather than remove the task link.