Some milestones may need a duration. For example, your project has an approval milestone at the end of a phase (phase: A group of related tasks that completes a major step in a project.) and you know that the approval process will take a week. To mark a task as a milestone with a duration of more than 0 days, click Task Information, and then click the Advanced tab. In the Duration box, enter the task duration, and then select the Mark task as milestone check box.