Microsoft Office Online
Sign in to My Office Online (What's this?) | Sign in

 
 
Microsoft Office Project
Search
Search
 
Icon: Flag: (c) Microsoft
Get up to speed
 
 
 
Warning: You are viewing this page with an unsupported Web browser. This Web site works best with Microsoft Internet Explorer 6.0 or later, Firefox 1.5, or Netscape Navigator 8.0 or later. Learn more about supported browsers.

Assignment Delay fields
 

The Assignment Delay fields show the amount of time a resource is to wait before starting work on an assignment. No information is actually displayed in the Assignment Delay task and resource fields; they merely make the corresponding Assignment Delay field information available.

There are several categories of Assignment Delay fields. Learn more about field categories.

Data Type  Duration (duration field: A type of field whose content is expressed as a duration of time. Examples include the Work, Duration, and Delay fields. A duration field includes the duration unit, such as hour, day, or week.)

ShowAssignment Delay (task field)

Entry Type  Null (Null field: A field that displays no actual information but that sets up the field for information elsewhere in the view, particularly in the Task Usage or Resource Usage view.)

Best Uses  Add the Assignment Delay task field to the Task Usage view when you want to display delay information for assignments under a task.

Example  You are reviewing delay information for assignments. You add the Assignment Delay field to the Task Usage view. Although no information appears in the Assignment Delay field next to the task names, the delay for their assignments appears in the assignment rows below each task name.

ShowAssignment Delay (resource field)

Entry Type  Null (Null field: A field that displays no actual information but that sets up the field for information elsewhere in the view, particularly in the Task Usage or Resource Usage view.)

Best Uses  Add the Assignment Delay resource field to the Resource Usage view when you want to display delay information for assignments under a resource.

Example  You are reviewing delay information for assignments. You add the Assignment Delay field to the Resource Usage view. No information appears in the Assignment Delay field next to the resource names. However, the delay for their assignments appears in the assignment rows below each resource name.

ShowAssignment Delay (assignment field)

Entry Type  Calculated or entered (calculated or entered field: A field in which the value is determined by Project based on information in other fields. Information that you enter in the field yourself overrides calculated values.)

How Calculated  Microsoft Office Project calculates any difference between the assignment start date and the task start date. This difference is the assignment delay.

Assignment Delay = Start (task) - Start (assignment)

If you enter an assignment start date that is later than the task start date, the assignment delay field will change to reflect the difference between the assignment start date and the task start date.

Best Uses  To have an assignment start sometime after the start of the task, enter a value in the Assignment Delay field. Add the Assignment Delay field to the Task Usage or Resource Usage view when you want to review, filter, or edit the assignment delay.

Example  The "Conduct client meetings" task is assigned to Sean, Chris, and Jamie, with a duration of 5 days. However, Jamie is not to be involved with the task until the final day. To schedule Jamie for the final day of the task, type 4d in the Assignment Delay field (and 1d in the Work field) for Jamie's assignment.

advertisement