| | Product Information Help and How-to Training Templates Related Products and Technologies Support and Feedback Technical Resources Additional Resources | Warning: You are viewing this page with an unsupported Web browser. This Web site works best with Microsoft Internet Explorer 6.0 or later, Firefox 1.5, or Netscape Navigator 8.0 or later. Learn more about supported browsers.
Goal: Put tasks, phases, or the project back on schedule
After you identify problems in your schedule, you can use a variety of strategies to manage your project dates. For example, you can simply change a task's duration, or you can adjust other factors affecting the schedule, such as dependencies (task dependencies: A relationship between two linked tasks; linked by a dependency between their finish and start dates. There are four kinds of task dependencies: Finish-to-start [FS], Start-to-start [SS], Finish-to-finish [FF], and Start-to-finish [SF].), constraints (constraint: A restriction set on the start or finish date of a task. You can specify that a task must start on or finish no later than a particular date. Constraints can be flexible [not tied to a specific date] or inflexible [tied to a specific date].), and resources (resources: The people, equipment, and material that are used to complete tasks in a project.). After you make the necessary adjustments, you should evaluate any effects your changes might have had on other projects and communicate changes to team members and stakeholders.
Tip This article is part of a series of articles
within the Project Map
that describe a broad set of project management activities.
We call these activities "goals" because they are organized around the project management life
cycle: Build a plan, track and manage a project, and close a project.
Previous goal | Next goal
See all goals on the Project Map
 |
Modify a task schedule One way to get back on schedule is to change specific settings on tasks that affect their length and their relationships to other tasks. For example, changing a task that starts after another task to starting at the same time can help bring in the finish date.
Click all of the following that apply:
Modify a resource schedule After you make changes to your plan, changing how you assign resources to critical tasks (critical task: A task that must be completed on schedule for the project to finish on time. If a critical task is delayed, the project completion date might also be delayed. A series of critical tasks makes up a project's critical path.) can also significantly improve the schedule.
Do all of the following that apply:
- Assign a resource to the team. Assigning more resources to tasks on the critical path can help decrease the durations of tasks and shorten the length of the project. A resource can be a single person, such as Ben Smith, or it can be a group, such as Architects. It can be a piece of equipment such as a crane or a computer. Or it can be material consumed in the course of accomplishing the task.
- Replace a resource assignment
if it will help tasks to finish earlier. You might want to replace a resource to resolve overallocations (overallocation: The result of assigning more tasks to a resource than the resource can accomplish in the working time available.), reduce costs, increase efficiency, or increase quality.
- Set working times, vacations, and holidays for your project
to decrease the duration of a task. This works because, by default, Project 2007 uses effort-driven scheduling (effort-driven scheduling: The default method of scheduling in Project; the duration of a task shortens or lengthens as resources are added or removed from a task, while the amount of effort necessary to complete a task remains unchanged.), which means that as work hours are added to a task, the duration of that task decreases.
- Update an interim plan so you can compare it
to your schedule as the project progresses.
You can save up to 10 interim plans so that you can view a set of start and finish dates saved at various stages of your project.
- Improve resource performance
by providing resources with training and better tools to do their jobs, by applying management skills to resource issues, and so on. Improving performance is sometimes the only solution if additional people are not available to help.
More . . .
An often overlooked means of keeping your schedule (schedule: The timing and sequence of tasks within a project. A schedule consists mainly of tasks, task dependencies, durations, constraints, and time-oriented project information.) on track is to improve resource (resources: The people, equipment, and material that are used to complete tasks in a project.) performance. Working with resources to improve performance is a complex topic, but you may be able to improve resource performance as part of project management
by using the following suggestions:
Evaluate the results of changing the schedule After you make changes to your plan, make sure you haven't affected the scheduling of other projects with dependencies in your project.
Click all of the following that apply:
- See what's driving the project finish date
to see how the changes you made to optimize for the finish date affected the critical path. This can help you see whether you actually achieved your goal of meeting your targeted finish date.
- View project date information to view date information for your project or for projects that have been published to Microsoft Office Project Server 2007.
- Review resource workloads to see whether any assigned resources are now overloaded or underutilized as a result of you optimizing the project plan to meet the finish date.
Communicate assignment changes to resources After you make changes to your project, you may need to communicate these changes to others, such as stakeholders and team members.
|
Previous goal | Next goal