Microsoft Office Online
Sign in to My Office Online (What's this?) | Sign in

 
 
Microsoft Office Project
Search
Search
 
Icon: Flag: (c) Microsoft
Get up to speed
 
 
 
Warning: You are viewing this page with an unsupported Web browser. This Web site works best with Microsoft Internet Explorer 6.0 or later, Firefox 1.5, or Netscape Navigator 8.0 or later. Learn more about supported browsers.

Set lead or lag time (float) between tasks
 

When you set up task dependencies (task dependencies: A relationship between two linked tasks; linked by a dependency between their finish and start dates. There are four kinds of task dependencies: Finish-to-start [FS], Start-to-start [SS], Finish-to-finish [FF], and Start-to-finish [SF].), there may be some successor (successor: A task that cannot start or finish until another task starts or finishes.) tasks that can start before their predecessor (predecessor: A task that must start or finish before another task can start or finish.) tasks are finished, and other successor tasks that cannot be started until after a delay that follows the conclusion of their predecessor tasks:

Lead time and lag time can be entered either as a duration (duration: The total span of active working time that is required to complete a task. This is generally the amount of working time from the start to finish of a task, as defined by the project and resource calendar.) (for example, two days after the completion of the task) or as a percentage of the duration of the predecessor task (for example, begin the task when the predecessor's duration is 50% complete).

  1. On the View menu, click Gantt Chart.
  2. In the Task Name field, select the task for which you want to set lead time or lag time, and then click Task Information Button image .
  3. Click the Predecessors tab.
  4. In the Lag field, type the lead time or lag time that you want, either as a duration or as a percentage of the duration of the predecessor task:
    • To enter lead time, type either a negative number or a negative percentage (such as -2d for two days of lead time).
    • To enter lag time, type either a positive number or a positive percentage (such as 50% for half of the predecessor task's duration in lag time).

  Notes  

  • You can set lead time or lag time between a maximum of two tasks, and the lead or lag time must be set after a dependency is created between those tasks.
  • You can quickly add lead time or lag time to a successor task by double-clicking the link line on the Gantt Chart view and then typing the amount or percentage of lead time or lag time in the Lag field.
Watch this video Demo buttonLag and lead time

Top of Page Top of Page