I moved some tasks, and the task dependencies changed
 

Symptoms

When you move some tasks (task: An activity that has a beginning and an end. Project plans are made up of tasks.), the task dependencies (task dependencies: A relationship between two linked tasks; linked by a dependency between their finish and start dates. There are four kinds of task dependencies: Finish-to-start [FS], Start-to-start [SS], Finish-to-finish [FF], and Start-to-finish [SF].) change.

Cause

When you copy or move an entire task or resource (resources: The people, equipment, and material that are used to complete tasks in a project.), the associated information is copied or moved with it. This information includes:

In addition, Project, by default, automatically creates task dependencies for new tasks that you insert within a series of consecutively linked tasks. If all of the following criteria are met, your dependencies will change to include the inserted task in the linked series:

  • The surrounding tasks are part of a series of consecutively linked tasks.
  • The dependencies for the surrounding tasks are finish-to-start.
  • The Autolink inserted or moved tasks check box is selected on the Schedule tab of the Options dialog box (Tools menu).

When you move a task within a group of linked tasks, Project links that task within the group's sequence (for example, A>B>C>D becomes A>B>D>C).

When you move a task from one group of linked tasks to another, the task is inserted into the sequence of the new group (for example, A>B>X>C>D), and the remaining tasks are adjusted (W>Y>Z).

When you move a task from a group of linked tasks to an area with no linked tasks, the moved task is unlinked, and the remaining tasks are adjusted (for example, A>B>C>D becomes A>B>D).

When you move a task from an area with no linked tasks to a group of linked tasks, the moved task is inserted into the sequence (for example, A>B>X>C>D).

Resolution

You can maintain task dependencies between any predecessor (predecessor: A task that must start or finish before another task can start or finish.) and successor (successor: A task that cannot start or finish until another task starts or finishes.) tasks, regardless of where you move the task, if at least one of the following criteria is met:

  • The task is not being moved from or pasted into a series of consecutively linked tasks.
  • The task being moved contains task dependencies other than finish-to-start.
  • The Autolink inserted or moved tasks check box is not selected on the Schedule tab of the Options dialog box (Tools menu).