What piece of the scheduling formula does not change when effort-driven scheduling is applied to a task?

The resource units assigned to a task.

Duration, the time it takes to complete the task.

The work (measured in time units) necessary to complete the task.

Even though the effort-driven setting is turned on by default in Project, it doesn't have any affect on your project schedule until:

You enter the total amount of work estimated for a task in the project schedule.

You add resources to or remove resources from a task.

You assign a value for the task's duration.